The resynchronization of Cernavoda NPP Unit 1 to the National Power Grid

Release Date: 8/5/2020 7:28:06 PM

IRIS Code: 9829E

Current report according to: ASF Regulation no. 5/2018 on issuers of financial instruments and market operations

Report date: 05.08.2020

Name of the issuing entity: NUCLEARELECTRICA S.A. National Company

Registered office: 65 Polona St., district 1, Bucharest

Telephone/Fax Number: 021-203.82.00 / 021 – 316.94.00

Sole Registration Code with the Trade Registry Office: 10874881

Registration number: J40/7403/1998

Subscribed and paid share capital: RON 3,015,138,510

Regulated market on which the issued securities are traded: Bucharest Stock Exchange

 

To: Bucharest Stock Exchange

Financial Supervision Authority

 

Significant event to report: The resynchronization of Cernavoda NPP Unit 1 to the National Power Grid

 

 

SN Nuclearelectrica SA informs its shareholders and investors that the works  related to the planned outage of Cernavoda NPP Unit 1 have been completed and that the resynchronization to the National Power Grid took place in the evening of 05.08.2020. Unit 1 entered the planned outage program on June 20th, 2020, in order to perform tha planned maintenance works, which are carried out once every 2 years for each unit. During the planned outage, over 10.000 activities were carried out from the following programs:

-          Preventive and corrective maitenance program

-          Inspection program

-          Mandatory testing program during the planned outage, in compliance with the requirements of the National Commission for the Control of Nuclear Activities, which can be performed only in shutdown mode;

-          Project modifications implementation program for certain systems/equipments/components.

The decision to enter the planned outage of Cernavoda NPP Unit 1 was delayed from the initial planned timeline, due to the international context generated by the COVID 19 pandemic coroborated with the measures provided in the Personnel Protection Plan, similar to other nuclear power plants, for ensuring the continuity of production and operation. The decision to enter the planned outage program of Cernavoda NPP Unit 1 starting with June 20th 2020 was adopted by the SNN Board of Directors in the meeting of May 8th 2020, based on the analysis of all factors bearing on the planned outage of Unit 1.

All the works carried out during the planned outage were performed with the strict observation of the nuclear safety measures and also the prevention measures against the spread of COVID 19 infection.

 

Cosmin Ghita

Chief Executive Officer



 Print

Information provided by IRIS, the news platform of the Bucharest Stock Exchange.

______________________

Bucharest Stock Exchange ("BVB") is not responsible for the content of this News item. Issuers whose financial instruments are traded on markets operated by BVB are required to report in accordance with current legal and regulatory provisions. BVB publishes these Reports as market administrator, appointed by ASF. When, for investors’ information, Reports are published, either signed by different persons, or with conflicting information, legal liability lies fully with the signatories. BVB disclaims any obligation or responsibility towards issuers or third parties, regarding the reality, completeness and accuracy of information provided by them and distributed by BVB. Website users are responsible for checking content. Any news item (including any prospectus) which is addressed solely to the persons and countries specified therein should not be relied upon other than by such persons and/or outside the specified countries. Terms and conditions, including restrictions on use and distribution apply.


©2016 Bucharest Stock Exchange. All rights reserved